# The Portishead Branch Line (MetroWest Phase 1) Order 2022, Paragraph 20: Temporary path at Avon Road, Pill

Extent: E+W

(1) Work No. 20 must not commence until written details of the levels and surfacing of the Work have been submitted to and approved by the relevant planning authority in consultation with the relevant highway authority. The Work must be carried out in accordance with the approved details prior to commencement of Work No. 20A or 20B. Work No. 20 must thereafter be retained and available for use for the duration of the use of Work No. 20B as a construction compound.
(2) Following cessation of use of Work No. 20B, Work No. 20 must be removed within 6 months to the satisfaction of the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2022/1194/schedule/2/paragraph/20 (the official version)
Page: https://openlegislation.uk/portishead-branch-line-metrowest-phase-1-order-2022/schedule-2/paragraph-20
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.