(1) Work No. 5 (Portishead Station) must not commence until written details of any permanent lighting to be installed in connection with that work, including measures to minimise light spillage, have been submitted to and approved by the relevant planning authority, the authority acknowledging the necessity for the lighting to comply with Railway Industry Standards.
(2) Work No. 5 must not commence until written details of any GSM-R mast to be located at Portishead Station have been submitted to and approved by the relevant planning authority. The GSM-R mast must not exceed 12 metres in height from the proposed track bed level of Work No. 1 at Portishead Station.
(3) Work No. 5 must not commence until written details of proposals for the inclusion of on-site energy generation to be incorporated within the detail design for Portishead Station have been submitted to and approved by the relevant planning authority.
(4) Work No. 5 must be carried out in accordance with the approved details.
(5) Work No. 3 (a foot and cycle track east of Portbury Ditch) and Work No. 5 must not commence until a Flood Risk Assessment (FRA) for those works has been submitted to and approved by the relevant planning authority in consultation with the Environment Agency. If the FRA concludes that Work No. 3 or Work No. 5 is at risk of flooding then the FRA must include details of the agreed mitigation works, to include a flood emergency and evacuation plan, that would be required for the relevant Work and users would remain safe should a flood event occur
(6) First commercial use must not occur prior to the approval of a station travel plan for Portishead Station by the relevant planning authority. The content of the station travel plan must substantially reflect the outline station travel plan for Portishead Station submitted as part of the Environmental Statement, as Volume 4, Technical Appendices, Appendix 16.1 Transport Assessment (Part 17 of 18) – Appendix M, Outline Station Travel Plans.

---
Source: https://www.legislation.gov.uk/uksi/2022/1194/schedule/2/paragraph/26 (the official version)
Page: https://openlegislation.uk/portishead-branch-line-metrowest-phase-1-order-2022/schedule-2/paragraph-26
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.