# The Portishead Branch Line (MetroWest Phase 1) Order 2022, Paragraph 28: Operational lighting – highways, bridges, paths and car parks

Extent: E+W

(1) Any part of the authorised development which includes—
(a) new highway lighting;
(b) new permissive paths or public rights of way including new lighting; or
(c) new car parks at Portishead or Pill including new lighting,
must not commence until written details of any permanent lighting to be installed in connection with the relevant work, including measures to prevent light spillage, have been submitted to and approved in writing by the relevant planning authority.
(2) Any approved means of lighting must be installed in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2022/1194/schedule/2/paragraph/28 (the official version)
Page: https://openlegislation.uk/portishead-branch-line-metrowest-phase-1-order-2022/schedule-2/paragraph-28
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.