# The Portishead Branch Line (MetroWest Phase 1) Order 2022, Part 1: Crossings extinguished: works required

Extent: E+W

(1)
Area
(2)
Accommodation facility to be discontinued
(3)
Rights to be extinguished
(4)
Works to be provided
In the District of North Somerset, Portbury
Crossing at 128 miles 46 chains at Shipway Gate Farm
All rights (if any) to use the crossing at Shipway Gate Farm between points S9 and S10 shown on sheet 2 of the crossings to be extinguished plans
New gate and works on the highway known as Sheepway marked N1 on sheet 2 of the crossings to be extinguished plan
In the District of North Somerset, Portbury
Crossing at 128 miles 39 chains at Shipway Gate Farm
All rights (if any) to use the crossing at Shipway Gate Farm between the points S11 and S12 shown on sheet 2 of the crossings to be extinguished plans
New gate and works on the highway known as Sheepway marked N1 on sheet 2 of the crossings to be extinguished plans
In the District of North Somerset, Portbury
Crossing at 128 miles 17 chains at Elm Tree Farm, Portbury
All rights (if any) to use the crossing to the South of Sheepway and to the west of Elm Tree Farm between the points S13 and S14 shown on sheet 3 of the crossings to be extinguished plans
New gate and works on the highway known as Portbury Hundred marked N2 on sheet 3 of the crossings to be extinguished plans

---
Source: https://www.legislation.gov.uk/uksi/2022/1194/schedule/9/part/1 (the official version)
Page: https://openlegislation.uk/portishead-branch-line-metrowest-phase-1-order-2022/schedule-9/part-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.