In constructing the authorised works the City Council or a person authorised by the City Council to carry out the authorised works may deviate laterally from the lines or situations shown on the deposited plan to the extent of the limits of deviation and may divert vertically from the levels shown on the deposited sections to any extent not exceeding 3 metres upwards and to such extent downwards as may be found necessary or convenient.

---