# The Portsmouth (Continental Ferry Port Berth 2 Extension) Harbour Revision Order 2011, Article 6: Further powers as to works

Extent: E+W+S
Status: repealed

Subject to the provisions of this Order, the City Council or a person authorised by the City Council to carry out the authorised works may, in connection with the construction of those works, enclose and reclaim from the foreshore and bed of the sea, and may hold and use as part of the Mile End Quay undertaking, so much of the foreshore and bed of the sea as is situated within the limits of deviation and is required for, or in connection with, the construction of those works.

---
Source: https://www.legislation.gov.uk/uksi/2011/3032/article/6 (the official version)
Page: https://openlegislation.uk/portsmouth-continental-ferry-port-berth-2-extension-harbour-revision-order-2011/article-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.