Article 5 Power to construct works
Subject to the provisions of this Order, the Council may, when they have acquired the necessary lands or obtained sufficient interests therein, make and maintain, within the limits of deviation shown therefor upon the deposited plan the following works in the City of Portsmouth:—
-
Work No. 1 — A wharf and quay and an embankment and reclamation north and west of the existing Mile End Quay within an area of land enclosed by an imaginary line commencing at the northern end of the western face of the existing Rudmore Quay of the Company, passing in a westerly direction for a distance of 151 metres, thence turning to and passing in a south-westerly direction for a distance of 203 metres, thence in a south-easterly direction for a distance of 22 metres to a point on the north-west embankment of the existing Mile End Quay, thence passing generally along the northern face of the Mile End Quay to Mill Wharf and thence along the seaward face of Mill Wharf and Rudmore Quay to the point of commencement;
-
Work No. 2 — Two breasting dolphins situated with their north-west faces on a line extending north-eastward from the northern end of the quay (Work No. 1), comprising—
-
Work No. 2A — One such dolphin centred at a point 20 metres from the said northern end of that quay; and
-
Work No. 2B — One such dolphin centred at a point 47 metres from the said northern end of that quay.
The Council may within the limits of deviation therefor extend, enlarge, alter, replace or relay the authorised works.