# The Preesall Underground Gas Storage Facility Order 2015, Article 42: Requirements

Extent: E+W

(1) Schedule 9 (Requirements) has effect.
(2) Save for paragraph 4(1) and (2) (detailed design approval) of Schedule 9 (Requirements), Schedule 9 shall not apply to—
(a) Work Nos. 16J, 16K and 16L of Schedule 1 (authorised development) so far as these fall within the UK marine area; and
(b) the incorporation of filters into the existing water intake structure comprised in Work No. 15 of Schedule 1 (authorised development).

---
Source: https://www.legislation.gov.uk/uksi/2015/1561/article/42 (the official version)
Page: https://openlegislation.uk/preesall-underground-gas-storage-facility-order-2015/article-42
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.