# The Preesall Underground Gas Storage Facility Order 2015, Paragraph 26: Licence conditions during construction of the licensed works

Extent: E+W

(1) The licence holder shall in the course of any stage of construction of the licensed works take appropriate steps to minimise damage to the foreshore, including to key BAP habitats so far as they are located on the foreshore. Details of such steps, and for steps to identify damage caused (if any) by the construction of the licensed works to key BAP habitats so far as they are located on the foreshore, shall be included in the method statement for that stage to be submitted for approval under paragraph 17.
(2) For the purposes of this paragraph, “the foreshore” means land which is covered and uncovered by the ordinary movement of the tide.

---
Source: https://www.legislation.gov.uk/uksi/2015/1561/schedule/7/paragraph/26 (the official version)
Page: https://openlegislation.uk/preesall-underground-gas-storage-facility-order-2015/schedule-7/paragraph-26
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.