# The Preesall Underground Gas Storage Facility Order 2015, Paragraph 3: Approval of plans

Extent: E+W

The promoter shall, before commencing the construction of any part of the specified works, furnish to the engineer such proper and sufficient plans relevant to the part of the specified works concerned as may be reasonably required by the engineer; and the promoter shall not commence those specified works until the plans have been approved in writing by the engineer or settled by arbitration under article 41 (arbitration).

---