# The Preesall Underground Gas Storage Facility Order 2015, Paragraph 22: Construction of and drilling operations in wellhead compound areas

Extent: E+W

(1) Wellhead compound areas (including the erection of associated bunds and temporary screening) shall not be constructed other than during the months of May to August (inclusive) in the same calendar year.
(2) Drilling operations within wellhead compound areas shall take place at no more than one wellhead compound area at any one time.

---