Regulation 3 Transitional provisions
Nothing in these Regulations affects any procurement commenced before the day on which these Regulations come into force.
For the purposes of paragraph (1), a procurement is commenced before the day on which these Regulations come into force if, before that day—
a tender notice has been published in accordance with section 21 (tender notices and associated tender documents) of the Procurement Act 2023;
a transparency notice has been published in accordance with section 44 (transparency notices) of that Act;
a below-threshold tender notice has been published in accordance with section 87 (regulated below-threshold contracts: notices)f1 of that Act;
a contracting authority has invited the submission of tenders in relation to a regulated below-threshold contract (see section 85(1) (regulated below-threshold contracts: procedure) of that Act);
in respect of a below-threshold contract to which neither sub-paragraph (c) nor (d) applies, a contracting authority has contacted a supplier in order to commence the award of that contract.
Annotations
Footnotes
- f1
-
Section 87(4) was amended by S.I. 2024/782 (W. 121).