# The Progress Power (Gas Fired Power Station) (Correction) Order 2016, Introduction: Introductory text


Infrastructure Planning
Made 11th July 2016
Coming into force 12th July 2016
The Progress Power (Gas Fired Power Station) Order 2015, which granted development consent within the meaning of the Planning Act 2008 (“the Act”), contains correctable errors within the meaning of the Act.
Before the end of the relevant period, as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a written request from the applicant for the correction of errors and omissions in the Progress Power (Gas Fired Power Station) Order 2015 under paragraph 1 (5)(a) of Schedule 4 to the Act.
The Secretary of State has informed Mid-Suffolk District Council and Suffolk County Council, the local planning authorities for the area in which the land to which the Progress Power (Gas Fired Power Station) Order 2015 relates is situated, that the request has been received and the statement issued, in accordance with paragraph 1(7) of Schedule 4 to the Act.
The Secretary of State, in exercise of the powers conferred by paragraph 1(4) and (8) of Schedule 4 to the Act, makes the following Order—

---
Source: https://www.legislation.gov.uk/uksi/2016/736/introduction (the official version)
Page: https://openlegislation.uk/progress-power-gas-fired-power-station-correction-order-2016/introduction
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.