# The Progress Power (Gas Fired Power Station) Order 2015, Article 37: Certification of plans etc.

Extent: E+W

(1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of—
(a) the book of reference;
(b) the design principles statement;
(c) the ecological management strategy;
(d) the environmental statement;
(e) the flood risk assessment;
(f) the important hedgerow plan;
(g) the land plans;
(h) the landscape mitigation strategy;
(i) the outline construction environment management plan;
(j) the outline construction traffic management plan;
(k) the outline landscaping plans;
(l) the outline lighting strategy;
(m) the rights of way, streets and access plan;
(n) the stage 2 written scheme of archaeological investigation; and
(o) the works plans
for certification that they are true copies of the documents referred to in this Order.
(2) A plan or document so certified is to be admissible in any proceedings as evidence of the contents of the document of which it is a copy.

---
Source: https://www.legislation.gov.uk/uksi/2015/1570/article/37 (the official version)
Page: https://openlegislation.uk/progress-power-gas-fired-power-station-order-2015/article-37
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.