# The Progress Power (Gas Fired Power Station) Order 2015, Paragraph 14: Construction Travel Plan

Extent: E+W

(1) No part of the authorised development may commence until a construction worker travel plan has been submitted to and approved by the relevant planning authority in consultation with the highway authority. The construction worker travel plan must be in accordance with the travel plan (other than the measures which relate to the operational phase).
(2) The construction worker travel plan must be carried out as approved.

---
Source: https://www.legislation.gov.uk/uksi/2015/1570/schedule/2/paragraph/14 (the official version)
Page: https://openlegislation.uk/progress-power-gas-fired-power-station-order-2015/schedule-2/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.