OpenLegislation

Regulation 12 The restricted procedure

Changes not yet applied. Later legislation changes this provision in ways not yet written into the text below:

–

(1)

A contracting authority using the restricted procedure shall comply with the following paragraphs of this regulation.

(2)

The contracting authority shall publicise its intention to seek offers in relation to the public works contract by sending to the Official Journal as soon as possible after forming the intention a notice, in a form substantially corresponding to that set out in Part C of Schedule 2, inviting requests to be selected to tender and containing the information therein specified in relation to the contract.

(3)

Subject to paragraph (14) below, the date which the contracting authority shall fix as the last date for the receipt by it of requests to be selected to tender shall be specified in the contract notice and shall be not less than 37 days from the date of the despatch of the notice.

(4)

The contracting authority may exclude a contractor from those persons from whom it will make the selection of persons to be invited to tender only if the supplier may be treated as ineligible on a ground specified in regulation 14 or if the contractor fails to satisfy the minimum standards of economic and financial standing and technical capacity required of contractors by the contracting authority; for this purpose the contracting authority shall make its evaluation in accordance with regulations 14, 15, 16 and 17.

(5)

The contracting authority shall make the selection of the contractors to be invited to tender in accordance with regulations 14, 15, 16 and 17; and in making the selection and in issuing invitations the contracting authority shall not discriminate between contractors on the grounds of their nationality or the member State in which they are established.

(6)

The contracting authority may predetermine the range within which the number of persons which it intends to invite to tender for the contract shall be fixed but only if–

(a)

the lower number of the range is not less than 5 and the higher number not more than 20,

(b)

the range is determined in the light of the nature of the work to be carried out under the contract, and

(c)

the range is specified in the contract notice.

(7)

The number of persons invited to tender shall be sufficient to ensure genuine competition.

(8)

The contracting authority shall send invitations to each of the contractors selected to tender and the invitation shall be accompanied by the contract documents, or the invitation shall state the address for requesting them.

(9)

The invitation shall be sent in writing simultaneously to each contractor selected to tender.

(10)

The following information shall be included in the invitation–

(a)

the address to which requests for the contract documents (if not accompanying the invitation) and further information relating to those documents should be sent, the final date for making such a request and the amount and terms of the fee which may be charged for supplying that material;

(b)

the final date for the receipt of tenders, the address to which they must be sent and the language or languages in which they must be drawn up;

(c)

a reference to the contract notice published in accordance with paragraph (2) above;

(d)

an indication of the information to be included with the tender which the contracting authority may require to be provided in accordance with regulations 15, 16 and 17; and

(e)

the criteria for the award of the contract if this information was not specified in the contract notice published in accordance with paragraph (2) above.

(11)

Subject to paragraphs (12) and (14) below, the date which the contracting authority shall fix as the last date for the receipt by it of tenders made in response to the invitation to tender which shall be specified in the invitation to tender in accordance with paragraph (10)(b) above shall not be less than 40 days from the date of the despatch of the invitation but, if it is necessary that contractors should be given the opportunity to inspect the premises on which the works under the contract are to be carried out or documents relating to the contract documents, then that minimum period shall be extended to allow for such inspection.

(12)

Subject to paragraph (14) below, where the contracting authority has published a notice in accordance with regulation 9 in relation to the public works contract, it may substitute for the period of not less than 40 days in paragraph (11) above a period of not less than 26 days.

(13)

Subject to paragraph (14) below, the contracting authority shall supply such further information relating to the contract documents as may reasonably be requested by a contractor selected to tender provided that the request for such information is received in sufficient time to enable the contracting authority to supply it not less than 6 days before the date specified in the invitation to tender as the final date for the receipt of tenders.

(14)

Where compliance with the minimum periods referred to in paragraphs (3), (11), (12) and (13) above is rendered impracticable for reasons of urgency, the contracting authority may substitute for the period specified in paragraph (3) a period of not less than 15 days and for the periods specified in (11) and (12) periods of not less than 10 days and for the period specified in paragraph (13) a period of not less than 4 days and, in those circumstances, the contracting authority must send the invitation to tender by the most rapid means possible.

(15)

A contracting authority shall not refuse to consider an application to be invited to tender if it is made by letter, telegram, telex, facsimile or telephone provided that, in the last 4 cases, it is confirmed by letter before the date fixed by the contracting authority as the last date for the receipt of requests to be selected to tender.