# The Railtrack (Leeds Bridges) Order 1999, Schedule 5: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN


(1)
(2)
(3)
(4)
Area
Number of land shown on deposited plans
Purpose for which temporary possession may be taken
Authorised work
City of Leeds
1 (part), 2 (part), 3 (part) and 6 (part)
Provision of working sites for construction purposes
Work No. 1
8 (part), 9 (part), 11 (part), 12 (parts) and 13
Provision of working sites for construction purposes
Work No. 2
14 (part), 15 (part), 17 (part), 18 (part), 20 (part) and 21 (part)
Provision of working sites for construction purposes
Work No. 3

---
Source: https://www.legislation.gov.uk/uksi/1999/2336/schedule/5 (the official version)
Page: https://openlegislation.uk/railtrack-leeds-bridges-order-1999/schedule-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.