# The Rampion 2 Offshore Wind Farm Order 2025, Paragraph 11: Offshore Decommissioning

Extent: E+W+S

No offshore works may commence until a written decommissioning programme in compliance with any notice served upon the undertaker by the Secretary of State pursuant to section 105(2) of the 2004 Act has been submitted to the Secretary of State for approval.

---
Source: https://www.legislation.gov.uk/uksi/2025/468/schedule/1/paragraph/11 (the official version)
Page: https://openlegislation.uk/rampion-2-offshore-wind-farm-order-2025/schedule-1/paragraph-11/enacted
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.