# The Rampion 2 Offshore Wind Farm Order 2025, Paragraph 32: Operational Travel Plan

Extent: E+W+S

(1) Prior to the commencement of the operation of the authorised development an operation travel plan which must accord with the outline operational travel plan must be submitted to, and approved by, the relevant planning authority following consultation with West Sussex County Council as highway authority.
(2) The approved operation travel plan must be implemented throughout the operational life of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2025/468/schedule/1/paragraph/32 (the official version)
Page: https://openlegislation.uk/rampion-2-offshore-wind-farm-order-2025/schedule-1/paragraph-32
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.