  "heading": "THE AUTHORISED DEVELOPMENT",
  "text": "Work No. 6—\nlandfall connection works comprising up to four cable circuits and associated ducts laid underground by horizontal directional drilling within the Order limits seaward of MHWS and landward of MLWS connecting Work No. 5 (b) and Work No. 7.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "F",
      "label": "F1",
      "text": "Word in Sch. 1 Pt. 1 para. 1 inserted (24.4.2026) by The Rampion 2 Offshore Wind Farm (Correction) Order 2026 (S.I. 2026/465), art. 1, Sch."
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/468/schedule/1/part/1",
    "retrieved_at": "2026-10-28T21:17:16.550102+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}