# The Rampion 2 Offshore Wind Farm Order 2025, Paragraph 7: Prior approvals and security

Extent: E+W+S

(1) The specified works must not commence until—
(a) a stage 1 and stage 2 road safety audit has been carried out and all recommendations raised by them or any exceptions are approved by National Highways;
(b) the programme of works has been approved by National Highways;
(c) the detailed design of the specified works comprising of the following details, insofar as considered relevant by National Highways, has been submitted to and approved by National Highways—
(i) the detailed design information, incorporating all recommendations and any exceptions approved by National Highways under sub-paragraph (a);
(ii) details of the proposed road space bookings;
(iii) the identity and suitability of the contractor and nominated persons;
(iv) a process for stakeholder liaison; and
(v) information demonstrating that the walking, cycling and horse riding assessment and review process undertaken by the undertaker in relation to the specified works has been adhered to in accordance with DMRB GG142 – Designing for walking, cycling and horse riding;
(d) a scheme of traffic management has been submitted by the undertaker and approved by National Highways such scheme to be capable of amendment by agreement between the undertaker and National Highways from time to time;
(e) stakeholder liaison has taken place in accordance with the process for such liaison agreed between the undertaker and National Highways under sub-paragraph (c)(iv) above;
(f) the undertaker has procured to National Highways collateral warranties in a form approved by National Highways from the contractor and designer of the specified works in favour of National Highways to include covenants requiring the contractor and designer to exercise all reasonable skill care and diligence in designing and constructing the specified works, including in the selection of materials, goods, equipment and plant; and
(g) a condition survey and regime of monitoring of any National Highways assets or structures that National Highways considers will be affected by the specified works, has been agreed in writing by National Highways.
(2) The undertaker must not exercise—
(a) article 4 (power to maintain the authorised project);
(b) article 9 (street works);
(c) article 11 (temporary closure of streets);
(d) article 17 (discharge of water);
(e) article 18 (protective work to buildings);
(f) article 19 (authority to survey and investigate the land onshore);
(g) article 22 (compulsory acquisition of land);
(h) article 24 (compulsory acquisition of rights and imposition of restrictive covenants);
(i) article 31 (temporary use of land for carrying out the authorised project);
(j) article 32 temporary use of land for maintaining the authorised project); or
(k) article 42 (felling or lopping of trees and removal of hedgerows) of this Order,
over any part of the strategic road network without the consent of National Highways, and National Highways may in connection with any such exercise require the undertaker to provide details of any proposed road space bookings and/or submit a scheme of traffic management for National Highways’ approval.
(3) National Highways must prior to the commencement of the specified works or the exercise of any power referenced in sub-paragraph (2) inform the undertaker of the identity of the person who will act as a point of contact on behalf of National Highways for consideration of the information required under sub-paragraphs (1) or (2).
(4) Any approval of National Highways required under this paragraph—
(a) must not be unreasonably withheld;
(b) must be given in writing; and
(c) may be subject to any conditions as National Highways considers necessary.
(5) Any change to the identity of the contractor and/or designer of the specified works will be notified to National Highways immediately and details of their suitability to deliver the specified works will be provided on request along with collateral warranties in a form agreed by National Highways.
(6) Any change to the detailed design of the specified works must be approved by National Highways in accordance with paragraph 7(1) of this Part.

---
Source: https://www.legislation.gov.uk/uksi/2025/468/schedule/10/part/7/paragraph/7 (the official version)