# The Rampion 2 Offshore Wind Farm Order 2025, Paragraph 13: Safety Zones

Extent: E+W+S

The authorised scheme or relevant part thereof must not commence until (insofar as relevant to the part of the authorised scheme) an application has been made to the Secretary of State for a safety zone for the relevant activities pursuant to the 2004 Act.

---
Source: https://www.legislation.gov.uk/uksi/2025/468/schedule/11/paragraph/13 (the official version)
Page: https://openlegislation.uk/rampion-2-offshore-wind-farm-order-2025/schedule-11/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.