# The Rampion 2 Offshore Wind Farm Order 2025, Paragraph 28: Piling restriction

Extent: E+W+S

No piling associated with the authorised development may be undertaken between 1 March to 31 July inclusive, unless otherwise agreed in writing by the MMO in consultation with the relevant statutory nature conservation body.

---
Source: https://www.legislation.gov.uk/uksi/2025/468/schedule/11/paragraph/28 (the official version)
Page: https://openlegislation.uk/rampion-2-offshore-wind-farm-order-2025/schedule-11/paragraph-28
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.