# The Rampion 2 Offshore Wind Farm Order 2025, Paragraph 8

Extent: E+W+S

No operation of any wind turbine generator forming part of the authorised development may begin until the Final KIMP has been implemented, and completed (where appropriate) and has been notified to the Secretary of State, and where the compensation comprises an artificial nesting structure this has been in place for at least four full kittiwake breeding seasons prior to such operation. For the purposes of this paragraph each breeding season is assumed to have commenced on 1 March in each year and ended on 31 August.

---