  "heading": "LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN",
  "text": "(1) Area\n(2) Number of land shown on onshore plan\n(3) Purpose for which temporary possession may be taken\n(4) Relevant part of the authorised project\nArun District\n2/10, 2/11, 2/15\nTemporary use as a construction compound and for access to facilitate construction of the authorised development, including any onshore Further Works, as defined in Schedule 1 to the Order, that may be required.\nWork No. 10\nHorsham District\n22/15, 33/12, 33/13\nArun District\n2/9, 3/10, 3/11, 3/12, 4/8\nTemporary use for the storage of excavated materials including but not limited to soil to facilitate construction of the authorised development, including any onshore Further Works, as defined in Schedule 1 to the Order, that may be required.\nWork No. 11\nHorsham District\n28/3, 29/3\nArun District\n2/27, 3/7\nTemporary use for non-intrusive works for duct and cable installation, preparation and stringing out, to facilitate construction of the authorised development, including any onshore Further Works, as defined in Schedule 1 to the Order, that may be required.\nWork No. 12\nHorsham District\n19/12, 22/26, 22/28, 22/29\nArun District\n1/19, 1/20, 1/22, 1/23, 1/25, 2/1, 2/16, 2/17, 2/18, 2/19, 2/20, 2/35, 2/36, 2/37, 3/3, 4/10, 4/11, 4/12, 4/13, 4/17, 4/18, 4/19, 4/20, 4/21, 7/7, 7/8, 7/9, 7/10, 7/11, 7/14, 7/15, 7/16, 7/17, 7/18, 7/19, 7/20, 7/21, 7/22, 11/14, 11/15, 12/2, 12/3, 12/6, 12/7, 12/8, 12/10, 12/11\nTemporary use for access, including effecting access to highways and the creation of visibility splays, to facilitate construction of the authorised development, including any onshore Further Works, as defined in Schedule 1 to the Order, that may be required.\nWork No. 13\nHorsham District\n16/1, 16/2, 16/3, 16/4, 16/5, 16/6, 17/2, 18/4, 18/5, 18/6, 21/11, 21/12, 21/13, 21/14, 21/15, 21/16, 21/17, 21/18, 21/19, 21/20, 21/21, 21/30, 21/31, 21/32, 21/33, 21/34, 21/35, 21/36, 21/37, 21/38, 22/16, 22/17, 22/19, 22/20, 22/21, 22/31, 22//32, 22/33, 23/5, 23/6, 23/10, 23/11, 23/12, 23/13, 23/14, 23/15, 24/7, 24/8, 24/9, 26/8, 26/9, 26/10, 27/4, 27/5, 27/6, 27/8, 27/9, 27/11, 27/12, 27/13, 27/14, 28/5, 28/8, 28/9, 28/11, 28/13, 28/14, 28/15, 29/14, 29/15, 29/16, 30/6, 30/8, 30/9, 30/10, 33/4, 33/5, 33/6, 33/7, 33/8, 33/21, 33/22\nMid-Sussex District\n34/6, 34/7, 34/8, 34/15, 34/31, 34/32, 34/33, 34/34, 34/35, 34/36, 34/37, 34/38, 34/39, 34/41",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 9 in force at 28.4.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/468/schedule/9",
    "retrieved_at": "2026-10-28T21:17:16.550102+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}