# The Rampion Offshore Wind Farm Order 2014, Paragraph 13: Highway accesses

Extent: E+W+S

(1) No stage of the connection works shall commence until written details of the siting, design, degree of permanence and layout of—
(a) any new permanent means of access to a highway outside the South Downs National Park to be used by vehicular traffic for that stage; or
(b) any new temporary means of access to a highway to be used by vehicular traffic for that stage; or
(c) any alteration to an existing means of access to a highway used by vehicular traffic for that stage,
has been submitted to and approved by West Sussex County Council or, where such access is directly to or from a trunk road, the Secretary of State for Transport.
(2) The highway accesses shall be constructed in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2014/1873/schedule/1/paragraph/13 (the official version)
Page: https://openlegislation.uk/rampion-offshore-wind-farm-order-2014/schedule-1/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.