# The Rampion Offshore Wind Farm Order 2014, Paragraph 33: External lighting and control of artificial light emissions

Extent: E+W+S

(1) No stage of the connection works outside the South Downs National Park where artificial lighting is required shall commence until written details of any external lighting to be installed in connection with that stage, including measures to prevent light spillage has been submitted to and approved by West Sussex County Council; any approved means of lighting shall subsequently be installed as approved.
(2) Work No. 25 shall not be commenced until a written scheme for the management and mitigation of artificial light emissions during the operation of Work No. 25 has been submitted to and approved in writing by West Sussex County Council.
(3) The approved scheme for the management and mitigation of artificial light emissions shall be implemented before and maintained during the operation of Work No. 25.

---
Source: https://www.legislation.gov.uk/uksi/2014/1873/schedule/1/paragraph/33 (the official version)
Page: https://openlegislation.uk/rampion-offshore-wind-farm-order-2014/schedule-1/paragraph-33
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.