# The Rampion Offshore Wind Farm Order 2014, Paragraph 5: Acquisition of land

Extent: E+W+S

Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference, the undertaker shall not acquire any apparatus or override any easement or other interest of a protected undertaker or acquire any land or other interest of a protected undertaker or create any new rights over the same otherwise than by agreement such agreement not to be unreasonably withheld or delayed.

---
Source: https://www.legislation.gov.uk/uksi/2014/1873/schedule/12/part/3/paragraph/5 (the official version)
Page: https://openlegislation.uk/rampion-offshore-wind-farm-order-2014/schedule-12/part-3/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.