# The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020, Article 35: Certification of plans etc.

Extent: E+W

(1) The undertaker must, as soon as practicable after the date on which this Order is made, submit to the Secretary of State copies of the documents listed in Schedule 9 (documents to be certified) for certification that they are true copies of the plans or documents referred to in this Order.
(2) A plan or document so certified is admissible in any proceedings as evidence of the contents of the plan or document of which it is a copy.

---
Source: https://www.legislation.gov.uk/uksi/2020/325/article/35 (the official version)
Page: https://openlegislation.uk/reinforcement-to-the-north-shropshire-electricity-distribution-network-order-2020/article-35
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.