# The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020, Article 4: Limits of deviation

Extent: E+W

In carrying out or maintaining the authorised development the undertaker may—
(a) subject to requirements 3 and 4, deviate from the lines or situations of the authorised development shown on the works plans and carry out construction and maintenance for the purposes of the authorised development anywhere within the Order limits; and
(b) deviate vertically from the levels of the authorised development set out in column 3 of Table 1 of requirement 3—
(i) to any extent not exceeding 2 metres upwards; or
(ii) to any extent downwards as may be found necessary or convenient.

---
Source: https://www.legislation.gov.uk/uksi/2020/325/article/4 (the official version)
Page: https://openlegislation.uk/reinforcement-to-the-north-shropshire-electricity-distribution-network-order-2020/article-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.