# The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020, Paragraph 11: A5(T) Traffic Management Crossing

Extent: E+W

No authorised development is to commence until, following consultation with Highways England, details of the construction traffic management for the temporary use of the existing A5(T) access (as shown in the Construction Accesses Location Plan, Environmental Statement: Appendix 1.4 Traffic and Transport Technical Note (July 2019)) and of the construction method for the installation of the underground cable (Work No. 2) under the A5(T) have been submitted to and approved by the relevant planning authority following written confirmation of approval of them by Highways England. The authorised works must be carried out in accordance with the details approved under this requirement.

---
Source: https://www.legislation.gov.uk/uksi/2020/325/schedule/2/paragraph/11 (the official version)
Page: https://openlegislation.uk/reinforcement-to-the-north-shropshire-electricity-distribution-network-order-2020/schedule-2/paragraph-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.