# The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020, Schedule 5: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

Extent: E+W

Table 3
(1) Location
(2) Number of land shown on land plans
(3) Purpose for which temporary possession may be taken
(4) Relevant part of the authorised development
East of the A5(T) near Long Wood at Middle
9
Temporary use as laydown area and access
Part of Work No.2 and Work No.3
East of the A5(T) near Long Wood at Middleton
10
Temporary use as laydown area
Part of Work No.2 and Work No.3
East of the A5(T) near Long Wood at Middleton
11
Temporary use as access
Part of Work No.2 and Work No.3
in Middleton between Cabin House and Top House Farm
16
Temporary use as laydown area
Part of Work No.3 and Work No.4
Southwest of Brookfield Farm, Coalpit Lane
39
Temporary use to dismantle existing LV overhead line
Part of Work No.4A
at Brookfield Farm, at the southern end of Coalpit Lane
45
Temporary use as laydown area
Part of Work No.3 and Work No.4
at Dandyford Farm near Lower Hordley
142
Temporary use as laydown area
Part of Work No.3 and Work No.4
at Top House Farm
186
Temporary use as laydown area
Part of Work No.3 and Work No.4
at Coppice Farm, southwest of Loppington
258
Temporary use as laydown area
Part of Work No.3 and Work No.4
on the western edge of Wem, in the field just south of Wem substation
375, 376
Temporary use as laydown area and for welfare unit and security cabin
Part of Work No.3 and Work No.4 and Work No.5

---
Source: https://www.legislation.gov.uk/uksi/2020/325/schedule/5 (the official version)
Page: https://openlegislation.uk/reinforcement-to-the-north-shropshire-electricity-distribution-network-order-2020/schedule-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.