# The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020, Paragraph 29

Extent: E+W

In the assessment of any sums payable to Network Rail under this Part, no account must be taken of any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by Network Rail if that action or agreement was not reasonably necessary or was taken or entered into with a view to obtaining the payment of those sums by the undertaker under this Part or increasing the sums so payable.

---
Source: https://www.legislation.gov.uk/uksi/2020/325/schedule/6/paragraph/29 (the official version)
Page: https://openlegislation.uk/reinforcement-to-the-north-shropshire-electricity-distribution-network-order-2020/schedule-6/paragraph-29
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.