# The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020, Paragraph 64: Arbitration

Extent: E+W

Save for differences or disputes arising under paragraphs 56(2), 56(4), 57(1), 58 any difference or dispute arising between the undertaker and National Grid under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and National Grid, be determined by arbitration in accordance with article 38 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2020/325/schedule/6/paragraph/64 (the official version)
Page: https://openlegislation.uk/reinforcement-to-the-north-shropshire-electricity-distribution-network-order-2020/schedule-6/paragraph-64
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.