# The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020, Paragraph 3: Fees

Extent: E+W

(1) Where an application is made to the relevant planning authority for consent, agreement or approval in respect of a requirement, a fee of £116 is to be paid to that authority.
(2) Any fee paid under this Schedule must be refunded to the undertaker within 42 days of—
(a) the application being rejected as invalidly made; or
(b) the relevant planning authority failing to determine the application within the decision period as determined under paragraph 1,
unless within that period the undertaker agrees, in writing, that the fee is to be retained by the relevant planning authority and credited in respect of a future application.

---
Source: https://www.legislation.gov.uk/uksi/2020/325/schedule/7/paragraph/3 (the official version)
Page: https://openlegislation.uk/reinforcement-to-the-north-shropshire-electricity-distribution-network-order-2020/schedule-7/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.