Rule 23 Ancillary provisions about delivery of nuclear administrator’s proposals
Paragraph (2) applies where the court orders, on an application by the nuclear administrator under paragraph 107 of Schedule B1 to the 1986 Act, an extension of the period in paragraph 49(5) of Schedule B1 to the 1986 Act for delivering copies of the statement of proposals.
As soon as reasonably practicable after the making of the order, the nuclear administrator must—
deliver a notice of the extension to every creditor of the relevant licensee nuclear company and every member of the relevant licensee nuclear company of whose address (in either case) the nuclear administrator is aware, and
deliver a copy of the notice of the extension to the registrar of companies.
The notice mentioned in paragraph (2) must—
be headed “Notice of extension of time period”;
include immediately below the heading—
the full name, registered address, registered number and any other trading names of the relevant licensee nuclear company;
details of the court where the proceedings are and the relevant court reference number;
state the date to which the court has ordered an extension.
Where the nuclear administrator wishes to publish a notice under paragraph 49(6) of Schedule B1 to the 1986 Act, the notice must—
be advertised in such manner as the nuclear administrator thinks fit;
be published as soon as reasonably practicable after the nuclear administrator has delivered the statement of proposals to the relevant licensee nuclear company’s creditors but no later than 8 weeks, or such other period as may be agreed by the creditors or as the court may order, from the date on which the relevant licensee nuclear company entered relevant licensee nuclear company administration.