# The Relevant Licensee Nuclear Company Administration (England and Wales) Rules 2023, Rule 86: Interpretation: final progress reports, etc.


In this Part—
“final progress report” means a progress report which includes a summary of—
(a) the nuclear administrator’s proposals,
(b) any major amendments to, or deviations from, those proposals,
(c) the steps taken during the relevant licensee nuclear company administration, and
(d) the outcome;
“progress report” means a report which complies with rule 26.

---
Source: https://www.legislation.gov.uk/uksi/2023/712/rule/86 (the official version)