# The Renewable Heat Incentive Scheme Regulations 2018, Paragraph 3: Secondary evidence (Category A)


For the purposes of paragraph 1(3)(a), the items of Category A evidence are—
(a) dated correspondence to the relevant planning authority seeking confirmation that the plant does not require planning permission;
(b) a dated enquiry to the local network operator about the grid connection of the plant;
(c) detailed, dated evidence (which can be from within the applicant’s organisation) that the applicant has allocated funding for the development of the plant;
(d) dated evidence that an estimated cost of works has been provided to the applicant.

---