# The Renewables Obligation (Amendment No. 2) Order (Northern Ireland) 2013, Article 3: Amount of electricity to be stated in NIROCs issued for electricity generated using pre-2013 capacity, 2013/15 capacity, summer 2015/16 capacity, winter 2015/16 capacity or post 2016 capacity


For parts 2C to 2E of Schedule 2 to the 2009 Order substitute—
“PART 2C
AMOUNT OF ELECTRICITY TO BE STATED IN NIROCs ISSUED FOR ELECTRICITY GENERATED USING PRE-2013 CAPACITY, 2013/15 CAPACITY OR SUMMER 2015/16 CAPACITY WHERE ARTICLE 26(1), (3), (4) OR (5) APPLIES
Article 26(1), (3), (4) and (5)
Generation type
Amount of electricity (in megawatt hours) to be stated in a NIROC issued in respect of the qualifying proportion of electricity generated using pre-2013 capacity, 2013/15 capacity or summer 2015/16 capacity
Amount of electricity (in megawatt hours) to be stated in a NIROC issued in respect of the remainder of the electricity generated using pre-2013 capacity, 2013/15 capacity or summer 2015/16 capacity
Co-firing of regular bioliquid with CHP
1
2
Dedicated biomass with CHP
1 2
2 3
High-range co-firing with CHP
5 7
10 9
Low-range co-firing with CHP
1
2
Mid-range co-firing with CHP
10 11
5 3
Station conversion with CHP
2 3
1
Unit conversion with CHP
2 3
1
PART 2D
AMOUNT OF ELECTRICITY TO BE STATED IN NIROCs ISSUED FOR ELECTRICITY GENERATED USING WINTER 2015/16 CAPACITY WHERE ARTICLE 26(6) APPLIES
Article 26(6)
Generation type
Amount of electricity (in megawatt hours) to be stated in a NIROC issued in respect of the qualifying proportion of electricity generated using winter 2015/16 capacity
Amount of electricity (in megawatt hours to be stated in a NIROC issued in respect of the remainder of the electricity generated using winter 2015/16 capacity
Co-firing of regular bioliquid with CHP
1
2
Dedicated biomass with CHP
10 19
2 3
High-range co-firing with CHP
5 7
10 9
Low-range co-firing with CHP
1
2
Mid-range co-firing with CHP
10 11
5 3
Station conversion with CHP
2 3
1
Unit conversion with CHP
2 3
1
PART 2E
AMOUNT OF ELECTRICITY TO BE STATED IN NIROCs ISSUED FOR ELECTRICITY GENERATED USING POST-2016 CAPACITY WHERE ARTICLE 26(7) APPLIES
Article 26(7)
Generation type
Amount of electricity (in megawatt hours) to be stated in a NIROC issued in respect of the qualifying proportion of electricity generated using post-2016 capacity
Amount of electricity (in megawatt hours) to be stated in a NIROC issued in respect of the remainder of the electricity generated using post-2016 capacity
Co-firing of regular bioliquid with CHP
1
2
Dedicated biomass with CHP
5 9
5 7
High-range co-firing with CHP
5 7
10 9
Low-range co-firing with CHP
1
2
Mid-range co-firing with CHP
10 11
5 3
Station conversion with CHP
2 3
1
Unit conversion with CHP
2 3
1
”

---
Source: https://www.legislation.gov.uk/nisr/2013/174/article/3 (the official version)
Page: https://openlegislation.uk/renewables-obligation-amendment-no-2-order-northern-ireland-2013/article-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.