# The Renewables Obligation (Amendment) Order (Northern Ireland) 2015, Article 3: Amendments to Article 27A (Qualifying new onshore wind stations and qualifying new solar photovoltaic stations)


For Article 27A(3) of the 2009 Order substitute—
“(3) The amount of electricity to be stated in each NIROC to be issued in respect of electricity generated by a qualifying new solar photovoltaic station to which this Article applies is—
(a) in relation to a 2010/2015 qualifying new solar photovoltaic station which has not had a declared net capacity in excess of 50 kilowatts at any time after 31st March 2010, 1 4 of a megawatt hour;
(b) in relation to a 2015/2016 qualifying new solar photovoltaic station which has not had a declared net capacity in excess of 50 kilowatts at any time after 30th September 2015, 1 3 of a megawatt hour;
(c) in relation to a 2016/2017 qualifying new solar photovoltaic station which has not had a declared net capacity in excess of 50 kilowatts at any time after 30th September 2016, 1 2 of a megawatt hour;
(d) in relation to a qualifying new solar photovoltaic station which has had a declared net capacity in excess of 50 kilowatts but not exceeding 250 kilowatts at any time after 31st March 2010, 1 2 of a megawatt hour.”.

---
Source: https://www.legislation.gov.uk/nisr/2015/287/article/3 (the official version)
Page: https://openlegislation.uk/renewables-obligation-amendment-order-northern-ireland-2015/article-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.