# The Renewables Obligation and Electricity Capacity (Amendment) (British Industrial Competitiveness Scheme Excluded Electricity) Regulations 2026, Regulation 7: Applications for BICS determinations


(1) An application for a BICS determination must be made to the Secretary of State in writing and must contain—
(a) the name of the individual submitting the BICS application on behalf of the BICS applicant, and an address and email address at which that individual can be contacted,
(b) evidence that the individual referred to in sub-paragraph (a) is authorised to submit the BICS application on behalf of the BICS applicant,
(c) the name, address and email address of the firm to which the BICS application relates, its registered number, and a statement as to whether that firm carries out activities in Northern Ireland,
(d) the address of the manufacturing site to which the BICS application relates and a statement as to whether or not it is shared with any other person and, if it is, the name of the person and, if available, an email address for the person,
(e) where a meter in respect of the manufacturing site—
(i) is registered in SMRS, the MSID that relates to that meter,
(ii) is registered in CMRS, the BM Unit Identification Number and MSID that relates to that meter,
(f) the address of each meter in respect of the manufacturing site,
(g) in the case of a private network boundary point meter, the name of the registered owner of the meter, being either a generator or an electricity supplier,
(h) a statement—
(i) confirming that all the electricity supplied to those meters is used in the course of business by the BICS applicant, or
(ii) identifying any person with whom that electricity is shared,
(i) where sub-paragraph (h)(ii) applies, evidence of the arrangements pursuant to which that electricity is shared,
(j) information identifying the electricity supplier who, when the BICS application is made, supplies the electricity which is measured by those meters and an address and email address for that supplier,
(k) the name of the person who pays the electricity supplier referred to in sub-paragraph (j) where that person is not the BICS applicant,
(l) where at the date of the BICS application the BICS applicant shares electricity supplied to the meters in respect of the manufacturing site or obtains electricity measured by those meters from a third party other than an electricity supplier—
(i) evidence of the amount of electricity measured by those meters which was supplied during the most recent six month period for which information is available in the 12 month period immediately prior to the making of the application, and
(ii) evidence of the proportion of the electricity measured by those meters that was used in the course of the BICS applicant’s business during the most recent six month period for which information is available in the 12 month period immediately prior to the making of the application,
(m) where at the date of the BICS application the BICS applicant obtains electricity measured by those meters from a third party other than an electricity supplier, evidence of the amounts charged by that third party and paid by the BICS applicant in relation to—
(i) the renewables obligation, and
(ii) the FIT Scheme,
(n) evidence that the BICS applicant is responsible for paying for the electricity to which the BICS application relates,
(o) if applicable, a statement identifying any third party, other than an electricity supplier, from whom the BICS applicant obtains electricity containing the third party’s address and, where available, email address,
(p) where sub-paragraph (o) applies, evidence of the arrangements pursuant to which the BICS applicant obtains electricity from a third party,
(q) evidence of the amount of electricity measured by the meters in respect of the manufacturing site which was supplied during the most recent six month period for which information is available in the 12 month period immediately prior to the making of the application,
(r) evidence of the specified activity for which electricity supplied to those meters is used in the course of business by the BICS applicant during the most recent six month period for which information is available in the 12 month period immediately prior to the making of the application,
(s) a statement setting out whether evidence is available of the proportion of electricity measured by the electricity meters in respect of a manufacturing site which is used for the specified activity,
(t) if the evidence in sub-paragraph (s) is available, such evidence for the most recent six month period for which information is available in the 12 month period immediately prior to the making of the application,
(u) a statement setting out the proportion, in accordance with regulation 8(2), (5), (6) or (7), as the case may be, of electricity measured by the electricity meters in respect of the manufacturing site which the BICS applicant reasonably considers should be BICS excluded electricity, and an explanation of why the BICS applicant reasonably considers it should be BICS excluded electricity,
(v) a statement setting out the—
(i) specified activities,
(ii) non-specified activities,
(iii) related activities, and
(iv) other activities,
which are carried out in the course of business by the BICS applicant at the manufacturing site to which the BICS application relates,
(w) a statement setting out whether the BICS applicant has an EII certificate,
(x) where at the date of the BICS application the BICS applicant has an EII certificate—
(i) evidence of that certificate,
(ii) evidence of the specified activity to which that certificate relates, and
(iii) a statement to the effect that the BICS application does not relate to any amount of electricity in respect of which the EII certificate is in force, and
(y) a declaration by the BICS applicant, made by an officer or agent duly authorised so to declare on behalf of the BICS applicant, that the information provided in the BICS application is correct and complete.
(2) For the purposes of paragraph (1)(c), “registered number” means the firm’s registered number in the register referred to in regulation 6(2)(a) in which it is entered.
(3) An application must be made before the 1st December preceding the BICS year.
(4) The Secretary of State may decide not to grant a BICS determination in respect of a BICS application where, in the opinion of the Secretary of State—
(a) the information or evidence contained in that application pursuant to paragraph (1) is not sufficient or not satisfactory, or
(b) the granting of the BICS determination would be incompatible with the United Kingdom’s international obligations in respect of subsidy control.

---
Source: https://www.legislation.gov.uk/uksi/2026/1171/regulation/7 (the official version)
Page: https://openlegislation.uk/renewables-obligation-and-electricity-capacity-amendment-british-industrial-competitiveness-scheme-excluded-electricity-regulations-2026/regulation-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.