# The Renewables Obligation Order 2015, Paragraph 18: Schedule 5 modified (electricity to be stated in ROCs)


(1) Schedule 5 has effect with the following modifications.
(2) In paragraph 1(1) of Part 1—
(a) omit the definition of “station conversion”;
(b) omit the definition of “station conversion with CHP”;
(c) in the definition of “unit conversion” omit paragraph (b) (and the “and” that precedes it);
(d) in the definition of “unit conversion with CHP” omit paragraph (b) (and the “and” that precedes it).
(3) In Part 2 in the table omit the whole row whose first entry is “station conversion”.
(4) In Part 3 in the table omit the whole row whose first entry is “station conversion”.
(5) In Part 5 in the table omit the whole row whose first entry is “station conversion with CHP”.
(6) In Part 6 in the table omit the whole row whose first entry is “station conversion with CHP”.
(7) In Part 7 in the table omit the whole row whose first entry is “station conversion with CHP”.

---
Source: https://www.legislation.gov.uk/uksi/2015/1947/schedule/6/paragraph/18 (the official version)
Page: https://openlegislation.uk/renewables-obligation-order-2015/schedule-6/paragraph-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.