# The Renewables Obligation Order 2015, Paragraph 9: New article 26A inserted


This Order has effect as if it were modified by inserting the following article after article 26—
“Meaning of RO input electricity: combustion units
26A. (1) This article applies for the purposes of this Part.
(2) In any month where the total installed capacity of a capped or exempt combustion unit of a mixed generating station does not include any excluded capacity, the “RO input electricity” of the unit is equal to—
A×BCwhere—
(a)A is the RO input electricity of the mixed generating station during that month (calculated in accordance with article 26);
(b)B is the total output electricity of the unit during that month; and
(c)C is the sum of the RO output electricity of each capped combustion unit and each exempt combustion unit of the mixed generating station during that month.
(3) In any month where the total installed capacity of a capped or exempt combustion unit of a mixed generating station includes excluded capacity, the “RO input electricity” of the unit is equal to—
A×BC×DEwhere—
(a)A, B and C have the meanings given in paragraph (2);
(b)D is the total installed capacity of the RO capacity of the unit; and
(c)E is the total installed capacity of the unit.”.

---
Source: https://www.legislation.gov.uk/uksi/2015/1947/schedule/6/paragraph/9 (the official version)
Page: https://openlegislation.uk/renewables-obligation-order-2015/schedule-6/paragraph-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.