# The Renewables Obligation Order (Northern Ireland) 2009, Article 27B: Qualifying new hydro stations


(1) This Article applies to a generating station which is a qualifying new hydro station.
(2) The amount of electricity to be stated in each NIROC which is issued in respect of electricity generated by a generating station to which this Article applies is—
(a) in relation to a qualifying new hydro station which has not had a declared net capacity in excess of 20 kilowatts at any time after 31st March 2010, ¼ megawatt hour;
(b) in relation to a qualifying new hydro station which has had a declared net capacity in excess of 20 kilowatts but not in excess 250 kilowatts at any time after 31st March 2010, ⅓ megawatt hour;
(c) in relation to a qualifying new hydro station which has had a declared net capacity in excess of 250 kilowatts but not in excess of 1 megawatt at any time after 31st March 2010, ½ megawatt hour;
(d) in relation to a qualifying new hydro station which has had a declared net capacity in excess of 1 megawatt but not in excess of 5 megawatts at any time after 31st March 2010, 1 megawatt hour.

---
Source: https://www.legislation.gov.uk/nisr/2009/154/article/27B (the official version)
Page: https://openlegislation.uk/renewables-obligation-order-northern-ireland-2009/article-27B
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.