# The Renewables Obligation Order (Northern Ireland) 2009, Article 27C: Qualifying new anaerobic digestion stations


(1) This Article applies to a generating station which is a qualifying new anaerobic digestion station.
(2) The amount of electricity to be stated in each NIROC which is issued in respect of electricity generated by a generating station to which this Article applies is—
(a) in relation to a qualifying new anaerobic digestion station which has not had a declared net capacity in excess of 500 kilowatts at any time on or after 26th April 2010, ¼ megawatt hour;
(b) in relation to a qualifying new anaerobic digestion station which has had a declared net capacity in excess of 500 kilowatts at any time on or after 26th April 2010, ⅓ megawatt hour.

---
Source: https://www.legislation.gov.uk/nisr/2009/154/article/27C (the official version)