Generation type
Amount of electricity (in megawatt hours) to be stated in a NIROC issued for electricity generated using—
2013/14 capacity
2014/15 capacity
AD
12
12
Advanced gasification/pyrolysis
12
12
Building mounted solar PV
1017
58
Co-firing of regular bioliquid
2
2
Dedicated biomass
23
23
Dedicated energy crops
12
12
Electricity generated from landfill gas
1
1
Electricity generated from sewage gas
2
2
Energy from waste with CHP
1
1
Geopressure
1
1
Geothermal
12
12
Ground mounted solar PV
58
58
High-range co-firing
109
109
Hydroelectric
107
107
Low-range co-firing
2
2
Mid-range co-firing
53
53
Offshore wind
12
12
Onshore wind
109
109
Standard gasification/pyrolysis
12
12
Station conversion
1
1
Tidal impoundment – tidal barrage
12
12
Tidal impoundment – tidal lagoon
12
12
Tidal stream
12
12
Unit conversion
1
1
Wave
12
12

---
Source: https://www.legislation.gov.uk/nisr/2009/154/schedule/2/part/2A (the official version)
Page: https://openlegislation.uk/renewables-obligation-order-northern-ireland-2009/schedule-2/part-2A
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.