# The Renewables Obligation (Scotland) Order 2009, Article 29: Microgenerators


(1) This article applies to a generating station which–
(a) is a microgenerator; and
(b) has not had a declared net capacity in excess of 50 kilowatts at any time after 31st March 2009.
(2) The amount of electricity to be stated in each SROC issued in respect of electricity generated—
(a) by a generating station to which this article applies; and
(b) using—
(i) pre-2013 capacity;
(ii) 2013/14 capacity; or
(iii) 2014/15 capacity,
is 12 of a megawatt hour.
(3) The amount of electricity to be stated in each SROC issued in respect of electricity generated—
(a) by a generating station to which this article applies; and
(b) using 2015/16 capacity,
is 1019 of a megawatt hour.
(4) The amount of electricity to be stated in each SROC issued in respect of electricity generated—
(a) by a generating station to which this article applies; and
(b) using post-2016 capacity,
is 59 of a megawatt hour.
(5) This article is subject to article 32.

---
Source: https://www.legislation.gov.uk/ssi/2009/140/article/29 (the official version)
Page: https://openlegislation.uk/renewables-obligation-scotland-order-2009/article-29
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.