# The Renewables Obligation (Scotland) Order 2009, Part 2A: AMOUNT OF ELECTRICITY TO BE STATED IN SROCs ISSUED FOR ELECTRICITY GENERATED USING 2013/14 CAPACITY, 2014/15 CAPACITY, 2015/16 CAPACITY OR POST-2016 CAPACITY


Generation type
Amount of electricity (in megawatt hours) to be stated in a SROC issued for electricity generated using—
2013/14 capacity
2014/15 capacity
2015/16 capacity
post-2016 capacity
AD
12
12
1019
59
Advanced gasification/
pyrolysis
12
12
1019
59
Building mounted solar PV
1017
58
23
57
Closed landfill gas
5
5
5
5
Co-firing of regular bioliquid
2
2
2
2
Dedicated biomass
23
23
23
57
Dedicated energy crops
12
12
1019
59
Electricity generated from sewage gas
2
2
2
2
Energy from waste with CHP
1
1
1
1
Enhanced tidal stream
13
13
13
13
Enhanced wave
15
15
15
15
Geopressure
1
1
1
1
Geothermal
12
12
1019
59
Ground mounted solar PV
58
57
1013
56
High-range co-firing
109
109
109
109
Hydroelectric
1
1
1
1
Landfill gas heat recovery
10
10
10
10
Low-range co-firing
2
2
2
2
Mid-range co-firing
53
53
53
53
Offshore wind
12
12
1019
59
Onshore wind
109
109
109
109
Standard gasification/
pyrolysis
12
12
1019
59
Station conversion
1
1
1
1
Tidal impoundment – tidal barrage
12
12
1019
59
Tidal impoundment – tidal lagoon
12
12
1019
59
Tidal stream
12
12
12
12
Unit conversion
1
1
1
1
Wave
12
12
12
12

---
Source: https://www.legislation.gov.uk/ssi/2009/140/schedule/2/part/2A (the official version)
Page: https://openlegislation.uk/renewables-obligation-scotland-order-2009/schedule-2/part-2A
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.