# The Renewables Obligation (Scotland) Order 2009, Part 2C: AMOUNT OF ELECTRICITY TO BE STATED IN SROCS ISSUED FOR ELECTRICITY GENERATED USING 2015/16 CAPACITY WHERE ARTICLE 28(5) APPLIES


Generation type
Amount of electricity (in megawatt hours) to be stated in a SROC issued in respect of the qualifying proportion of electricity generated using 2015/16 capacity
Amount of electricity (in megawatt hours) to be stated in a SROC issued in respect of the remainder of the electricity generated using 2015/16 capacity
Co-firing of regular bioliquid with CHP
1
2
Dedicated biomass with CHP
1019
23
High-range co-firing with CHP
57
109
Low-range co-firing with CHP
1
2
Mid-range co-firing with CHP
1011
53
Station conversion with CHP
23
1
Unit conversion with CHP
23
1

---
Source: https://www.legislation.gov.uk/ssi/2009/140/schedule/2/part/2C (the official version)
Page: https://openlegislation.uk/renewables-obligation-scotland-order-2009/schedule-2/part-2C
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.