# The Reservoirs Act 1975 (Capacity, Registration, Prescribed Forms, etc.) (England) Regulations 2013, Regulation 4: Registration requirements

Extent: E+W

(1) An undertaker must register a large raised reservoir with the Agency by providing the information described in Schedule 1, paragraphs 1 to 7.
(2) The information must be registered before the end of the period of 28 days beginning with the day of the issue of a final certificate given in accordance with section 7 of the 1975 Act in relation to—
(a) the construction of a new reservoir;
(b) the alteration of an existing structure of a reservoir that prior to its alteration was not a large raised reservoir; or
(c) the alteration of the area of a reservoir that prior to its alteration was not a large raised reservoir.

---
Source: https://www.legislation.gov.uk/uksi/2013/1677/regulation/4 (the official version)